Earned value (SPI / CPI)
Compare planned vs actual progress and cost.
Need saving, reports and the full analysis?Full professional version — Earned ValueProfessionalProject & Input Data
Embedded standards & references
- DOE EVMS Gold Card2019, EVM snapshot not schedule analysis
Results are engineering aids and require verification by a qualified professional before use on a real project.
Engineering Assumptions
Direct calculation — EVM snapshot and CPI scenario
- One horizon and one currency. EVM requires earned progress weighted by fixed baseline budgets; no financial-for-physical substitution or finish date from SPI. EAC is a scenario, not independent estimate.
- Delay is historical-average homogeneous-work scenario, not CPM or contractual delay forecast; zero progress gives no duration. Crew covers one work type at constant accepted output, no trade interchangeability or congestion effects.
- Period certificate is illustrative; tax is on gross work, not a country tax rule. Verify criteria first. Prior certificates remain frozen outside this tool; receipts, advance and retention stay separate, no approval or entitlement. Pricing is markup of loaded cost, not sales margin.
- https://www.energy.gov/sites/default/files/2019/07/f65/DOE%20EVMS%20Gold%20Card%2020190710.pdf
Formula Summary
- PV=BAC×planned%;EV=BAC×earned%;CV=EV−AC;SV=EV−PV
- CPI=EV/AC;SPI=EV/PV;scenarioEAC=BAC/CPI;undefined ratios omitted
Results
Enter your data and press Calculate to see the results.
Engineering Insight
Compare each balance separately; a rate, certificate or time valuation proves neither dates, acceptance nor receipts.
Recommended Action
Document baseline, horizon, quantities, rates and tax basis before accepting period arithmetic.
Next step
This calculator is fully usable as it is. Professional adds saved projects, calculation history and PDF/Excel reports; Premium adds the integrated workflows and the BOQ generator.