ProfessionalAvailable nowFull professional version
Earned Value
Project earned value indicators.
Want a quick result without signing in?Quick free version — Earned value (SPI / CPI)FreeThis calculator is part of a paid level
Unlock this calculator with a single purchase; access stays on your account for life.
Earned value turns four reported figures into an objective read on cost and schedule performance and a forecast at completion. Enter BAC, planned value, earned value and actual cost as of the data date, and the tool applies the standard EVM formulas exactly.
Method and assumptions
Earned Value Management (EVM) — PMI standard formulas
- CV=EV−AC; SV=EV−PV; CPI=EV/AC; SPI=EV/PV
- WR=BAC−EV; EAC(CPI)=AC+WR/CPI; EAC(composite)=AC+WR/(CPI×SPI)
- EAC(budget)=AC+WR; EAC(independent)=AC+ETC; EAC(recent)=AC+WR/CPI3
- CPI3=Σ incremental EV / Σ incremental AC for latest3 periods
- ETC=EAC−AC; VAC=BAC−EAC; TCPI(BAC)=WR/(BAC−AC); TCPI(EAC)=WR/ETC
- Cumulative values share scope, baseline and cutoff. PV and EV cannot exceed BAC. Zero-denominator indices are unavailable, not zero. User declares latest three consecutive periods; their totals cannot exceed cumulative values.
- SV and SPI are not critical-path dates; composite forecasting assumes schedule effects continue to influence costs. No universal prices or performance thresholds are assumed.
- Equation source: https://www.energy.gov/sites/default/files/2022-06/DOE%20EVMS%20Gold%20Card%20%2820190710%29.pdf
Frequently asked questions
- Which EAC formula is used?
- EAC = BAC ÷ CPI, the cumulative-CPI forecast. Other EAC variants are not applied.
- Where do PV, EV and AC come from?
- From your own cost and progress reporting at the data date. The tool does not measure progress; it only computes the indices.
- Is SPI a reliable schedule measure late in a project?
- SPI trends toward 1.0 as work completes regardless of delay, so read it with the critical path, not instead of it.
Next step and related links
Related calculators
- Cost-to-CompleteProject Control
- Progress AnalysisProject Control
- Project Cash FlowProject Control
Free calculators are open to everyone, and CSV export is free for everyone too. Project saving and PDF/Excel reports come with Professional, and integrated workflows with Premium.


