Site QA & HSE Kit

When to use it

When reviewing safety: compute the incident rate per 200,000 work hours to compare sites.

Recordable incident rate: incidents × 200,000 ÷ hours worked.

What you get after purchase

  • Five-hazard 5×5 register before and after with control level and verification: reductions credited only with evidence, administrative controls and PPE never cut severity; claimed versus credited.
  • Lagging indicators: LTIFR, TRIR and severity rate against your targets, the effect of one injury on the rate, and the near-miss ratio.
  • Leading indicators: inspections, training, permits and overdue actions with the weakest highlighted, plus three charts.
  • 49 inputs, eight metrics, four tables and three charts: claimed versus evidence-credited risk with control level, lagging rates against your targets and one-injury effect, and leading indicators for inspections, training, permits and actions. A monitoring tool, not a statutory assessment.
  • Bilingual 6-sheet Excel: consistency-checked controls, a 60-hazard register with verification and evidence references, 12 months with cumulative rates, 80 corrective actions at a fixed review date, and a decision sheet with three charts; invalid data blocks results.
  • Gift book: QA/QC, HSE & Passing Inspections.

A fixed-number teaching example, open to everyone before purchase, so you can see how it works.

Supporting your chances of success

This kit combines precise calculations with guidance and organisation to help you work towards your goal. We help you organise inputs, understand options and assess strengths and risks, then suggest practical steps suited to its subject — such as pricing, cash flow or marketing.

Guidance supports decisions, not guaranteed success; estimates depend on the accuracy of your inputs.

Understand the kit step by step

The kit answers two separate questions: is today's credited residual risk acceptable, and is the system preventing the next incident? A risk reduction is credited only for controls verified with evidence, and severity falls only through elimination, substitution or engineering controls. Lagging indicators (what happened) are read alongside leading indicators (inspections, training, permits and actions), never instead of them.

What to prepare before starting

For each hazard prepare likelihood and severity before and after, the highest control level applied and a signed inspection reference proving it is in place. For the period: hours worked, lost-time and recordable injuries, lost days, near misses, planned and completed inspections, training and permits, open and overdue actions, and company or contract targets.

From information to a decision

  1. Rate each hazard before controls: score = likelihood × severity on a 5×5 matrix.
  2. Record the controls, their highest level (1 elimination … 5 PPE) and the claimed rating after them.
  3. Credit the reduction only when verified with evidence; unverified stays at its before score, and administrative controls or PPE reduce likelihood only.
  4. Compute rates: LTI × 1,000,000 ÷ hours, recordables × 200,000 ÷ hours, severity = lost days × 200,000 ÷ hours, and note what one injury does to the rate.
  5. Read leading indicators as completion percentages; the weakest is this week's priority.
  6. In Excel record up to 60 hazards, 12 months and 80 actions at a fixed review date; verification without evidence, an action closed without evidence or in the future, or invalid data blocks results.

A simple example to explain the idea

Five hazards before controls: 20, 15, 15, 12 and 12. The highest claimed after controls is 10, but temporary-electricity controls are unverified so it stays at 12, making the highest credited risk 12 with two high risks. 450,000 hours, one lost-time injury, three recordables and 12 lost days: LTIFR 2.22 (target 2), TRIR 1.33 (target 1), severity 5.33, and one injury moves LTIFR by a full 2.22. 42 near misses = 14 per injury. Inspections, training and permits are each 85%, but 3 of 9 actions are overdue, so the weakest indicator is 66.7%.

These figures are illustrative, not approved prices or guaranteed forecasts; they may differ from the worked example below.

How to interpret and use the result

The gap between claimed and credited is missing evidence, not a safety improvement. Rates on few hours are unstable; read the cumulative trend together with leading indicators. Few near misses usually means under-reporting.

A common mistake to avoid

A monitoring tool, not a substitute for the statutory risk assessment, permits to work and a competent safety officer; never hide an injury to improve a rate, and targets come from company policy or contract, not a universal figure.

Reading the detailed operating plan

49 inputs, eight metrics, four tables and three charts: claimed versus evidence-credited risk with control level, lagging rates against your targets and one-injury effect, and leading indicators for inspections, training, permits and actions. A monitoring tool, not a statutory assessment.