MEP & HVAC Coordination Kit

When to use it

During coordination: track resolved and remaining clashes and the days needed to close them before construction.

Clash: two elements overlapping in drawings, such as a duct and a beam, to resolve before construction.

What you get after purchase

  • Clash tracking for four discipline pairs: found, resolved, open and resolved share.
  • Independent pair capacity, arrivals and reopens, critical/overdue, weekly backlog and required capacity; no automatic cross-discipline compensation.
  • Ceiling void check: ducts, insulation, sprinklers, cable trays and hangers under the beam, with the maximum achievable clear height.
  • 44 inputs, three tables and three charts: independent capacity for four pairs, arrivals, reopens, critical and overdue; arrangement, access and slope section check. Proposals are not closed; no automatic construction release.
  • Bilingual Excel file: clash register with status, owner and dates, a coordination meeting summary (open clashes per discipline pair, severity against status, items past target and average days open), and a ceiling void check sheet with formulas.
  • Gift book: Drawings & MEP/HVAC Coordination Field Guide.

A fixed-number teaching example, open to everyone before purchase, so you can see how it works.

Supporting your chances of success

This kit combines precise calculations with guidance and organisation to help you work towards your goal. We help you organise inputs, understand options and assess strengths and risks, then suggest practical steps suited to its subject — such as pricing, cash flow or marketing.

Guidance supports decisions, not guaranteed success; estimates depend on the accuracy of your inputs.

Understand the kit step by step

Practical workflow from clash register to documented closure, independent capacity per discipline pair, arrival/reopening scenarios and a preliminary section check. It does not automatically check models or authorize construction.

What to prepare before starting

Prepare clash ID, zone, model revision, both disciplines, owner, target and severity. Collect implemented-solution evidence, reviewer and verification date; determine three-week verified closure capacity plus arrival/reopening assumptions.

From information to a decision

  1. Deduplicate and record found and verified closed per pair; reject closures above found and fractional actual counts.
  2. Keep proposals open; close only after implementation on the revision and review with evidence/date. Preserve history on reopening.
  3. Critical and overdue are subsets of open and may overlap; never sum them. Separate open age from duration of closed items.
  4. Net pace per pair = capacity minus new arrivals minus reopens. Never use another pair's spare capacity. Nonpositive net gives no finite clearance time.
  5. Compare weekly path and required pace at issue; zero weeks means an immediate decision, not division by zero. Fractions are scenario averages, not verified closures.
  6. Review under-beam depth, service envelope, active gaps, access and slope level difference. Separate lanes require width evidence. Review issue meeting evidence with the professional.

A simple example to explain the idea

Unified review case: found12/14/8/6 and verified closed9/7/4/3; total40, closed23, open17, critical5 and overdue6 (possibly overlapping). Weekly capacity2/2/1/1; arrivals plus reopens0.5/1.25/0.75/0.5. After6 weeks backlog0/2.5/2.5/0 =5 forecast. Required weekly1/2.4167/1.4167/1. Available550mm, required1050mm including50mm access and50mm slope difference; shortage500mm, theoretical maximum clear2.20m, not a ceiling-lowering recommendation.

These figures are illustrative, not approved prices or guaranteed forecasts; they may differ from the worked example below.

How to interpret and use the result

Three tables and three charts separate pairs, priorities and section. Review workbook has eight sheets: Instructions, Control, Register, Pairs, Weeks, Section, Evidence, Decision;160 clashes and520 prepared weeks. Snapshot difference appears if register changes without controls. Review file is not the current customer download.

A common mistake to avoid

The check does not establish width, maintainability, code or hydraulic design; slope assumption is not a design standard. Evidence is a user-declared reference, not digital authentication. No ceiling/duct modification or drawing issue without engineering approval.

Reading the detailed operating plan

44 inputs, three tables and three charts: independent capacity for four pairs, arrivals, reopens, critical and overdue; arrangement, access and slope section check. Proposals are not closed; no automatic construction release.